5307 FEDERAL FISCAL YEAR 2023 UPDATES*
Total Funds Available for 2023 Capital Projects Section 5307: $7,889,462 after split
Activity | Fed Share | Total Price |
Preventative Maintenance | $1,760,000 | $2,200,000 |
Hardware | $160,000 | $200,000 |
*Surveillance | $601,139 | $751,424 |
Vehicle Replacement | $1,600,000 | $2,000,000 |
*Rehabilitation/Renovation Admin/Maintenance | $1,718,861 | $2,148,577 |
Rehabilitation/Renovation Bus Station | $2,049,462 | $2,561,828 |
Total Section 5307 Funded Items | $7,889,462 |
PARTIAL 5307 FEDERAL FISCAL YEAR 2024
Total Funds Available for 2024 Capital Projects Section 5307: $7,362,296 after split
Activity | Fed Share | Total Price |
Vehicle Replacement | $5,940,000 | $7,425,000 |
Total Section 5307 Funded Items | $5,940,000 |
Written public comments on the proposed Program of Projects will be accepted by the Toledo Area Regional Transit Authority until the close of business on May 31, 2024. Comments received by the closing date will be considered in preparing and carrying out the program. An opportunity for a public hearing will be offered if requested in the comments.
Comments can be submitted via mail to:
Chief Executive Officer
TARTA 1127 W Central Ave.
Toledo, OH 43610
Alternatively, you can email your comments with the subject line “Program of Projects” to Info@tarta.com.
This program will become final and will be submitted to the Federal Transit Administration on completion of the public participation process unless amended by the action of the Board of Trustees of the Toledo Area Regional Transit Authority.
Laura Koprowski, CEO
Empowering people to make connections.